Picnic Shelter Construction
4/9/2020 Timber Post Installation







5/2/2020 Roof Installation 1




5/9/2020 Roof Installation 2



6/14/2020 Roof Installation 3




7/10/2020 Gravel Poured and Plumbing Installation prior to Concrete




7/14/2020 Poured Concrete Installation


7/22/2020 Framing of the Walls




7/25/2020 Framing Completed





8/6/2020 OSB board and Wrap complete. Electrical started



8/18/2020 Sheet Metal Installed and Concrete Poured and Cut






10/2/2020 Insulation, Sheetrock Installable & Walls Painted





11/13/2020 Storage Room, Kitchen, Wood Ceiling







12/14/2020 Doors Installed, Storage Painted, Rough Grading